Techo International Airport

Engineering Cambodia’s New Icon

LBL International’s landmark contribution to the Techo International Airport: designing and delivering over 27,000 decorative panels and 612,000 custom-engineered pieces for Cambodia’s most ambitious project.

Panels Installed
Decorative aluminum panels designed & delivered
Team Mobilized
Skilled professionals deployed on-site
Surface Covered
Soffit ceilings & column cladding completed
Individual Pieces
Custom-modelled components assembled with precision

Project Scope

LBL’s Contribution to Techo International Airport

LBL International designed and built the iconic soffit ceilings and column cladding of Techo International Airport — more than 27,000 panels and 612,000 custom pieces covering 200,000 m² at heights up to 42 meters. Delivered on time through technical innovation and close collaboration with Foster + Partners, the project sets a new benchmark for architectural excellence in ASEAN.

From the Project Director

Engineering Trust Through Innovation

Our role at Techo International Airport was to design and build the soffit ceilings and column cladding — the signature elements of the terminal’s architecture.

The challenge was enormous: Foster + Partners’ design was still incomplete when we joined, ceilings rose more than 42 meters high, and over 600,000 pieces had to be assembled into 27,000 panels.

Through innovation, precision, and close collaboration with all stakeholders, we delivered on time and proved that LBL can tackle projects of global scale.

Dominique Desmet, Project Director

LBL created buildable, durable solutions faithful to Foster + Partners’ vision.

Custom scaffolding enabled safe installation of ceilings up to 42 meters high.

612,000 custom pieces and 27,000 panels assembled with digital precision.

Delivered in just 14 months through rigorous planning and coordination.

Impact Beyond Construction